Location
Built on the fourth floor, Banxuegang Telecom Building, Shenzhen, it is near from the offices of Huawei Technologies and Foxconn.

Construction
Area:1500 square meters
Anti-static floor
Aseismatic intensity: at the 8 degrees of earthquakes
Load-bearing capability: 850kg per square meter
5-meter ceiling height 
Power Guarantee
City Power Supply: City power supplies
UPS:Redundant(2+1)intelligent UPS system and sufficient battery
Generator Group :Backup diesel generator group, 1000Kw backup power supplies, and emergency refuel agreement with PetroChina for within-one-hour supplies ensure for constant operation.
Power supply: 99.99% 
Air-conditioner System
10 central air-conditioners with N+1 redundant backup
Air-flow: up-flow
Temperature: 18–26℃
Humidity: 40%–70% 
Cable Allocation System
Power cable route: under the raised floor
Communication cable route: upper the racks
Separated communication and power cables
ODF, DDF, MDF layout racks are available
Fire Prevention System
Burning Block Design: Burning-block material is adopted for walls, cages, floors, etc
Early smoke detection system:High-sensitive automatic system is used for early fire alarm.
Fire extinguishing system: CFM—200 intellectual extenuating system
24×7staff patrol 
Network
150Gbps connected with ChinaNet backbones, 4Gbps international bandwidths
Two nodes and two routers backup
Connecting layer:Connecting with carriers with independent Routers
Core layer:Backbones route gathering and data exchange to realize the high-speed transmitting
Gathering layer:Strategies carry out and application control
Access Layer:Multiple access ways and bandwidth control
Redundant route
Redundant chain
Redundant equipments
Redundant ports
Security System
7×24 live closed circuit TV monitoring
Biometric access control
24×7staff patrol  |